Boiler Work - framing and pouring concrete pads
- What
- Boiler Work - framing and pouring concrete pads
- When
- 10/6/2023, 6:30 AM – 5:00 PM
- Where
- Parking lot & rectory boiler room
| 12:31 PM (2 hours ago) | |||
|
Good afternoon Tina,
Update,
It sounds like the demo crew is all finished.
I will need to stop out to layout new configuration now that we have an open playing field. I plan to do this on Thursday and have our guys start this Friday.
They will be framing and pouring the pads for the new boilers on Friday. We will let the concrete cure over the weekend and plan on bringing sections down on Monday.
Monday we will need to bring in a small crane to off load the truck.
With this being said, we plan to put the crane next to the fence where the dumpster was and put our truck in the handicap spaces. We will need this area all day. Do you see this being an issue?
This means that the courtyard there will have to be closed. We will not be able to lift these boiler sections over people walking through there. Will this be an issue?
Please advise..
Thanks